Arraycom India – Head Office

Installation of 40 kW capacity Grid based Roof Top Solar project was done at our head office of Arraycom India Limited, Gandhinagar, Gujarat.

Type of plant                     : Grid tied Roof Top Solar

Plant capacity                    : 40 KW , 440 V , 3 Phase , 50 Hz

Roof top area                    : 400 sqm

Installed in                          : November 2016

Peak Power generation    :  222 Units Per Day

Savings till date                 :  Rs. 1.4 lacs in last 4 months

Module                                : Waaree – 315 W Multicrystal

Inverter                               : Growatt

Structure                             : Hot dip Galvanized

Execution                            : Solar power division team of Arraycom

Duration                             : 10 Days for full work completion